This project includes the work of widening I-84 to three lanes in each direction from MP 168 to MP 173 and replacing the eastbound and westbound 400 South Bridges (108' PRESTRESSED CONCRETE GIRDER BRIDGES). This Project contains 111,580 cubic yards of granular borrow and 70,583 cubic yards of excavation.
Additional Detail Items
Project Details Title
Contract Amount:
Project Details Item
$93,596,889.13
Project Details Title
Work Began Date:
Project Details Item
04/17/2023